Case Studies

California’s outdated project approval process is too often misused to delay or block essential projects our communities urgently need. From housing and schools to wildfire prevention and clean energy, critical projects are stalled for years—or stopped entirely—by endless bureaucracy, delays and lawsuits, driving up costs and leaving communities waiting.

Prop 45 modernizes this process by establishing clear timelines, improving accountability, and reducing unnecessary delays—so we can build essential projects faster and more affordably while maintaining strong environmental protections.

The case studies below are examples of real projects in California that have resulted in real delays and real costs.

Real Projects. Real Delays. Real Costs.

CalFire Vegetation Treatment Program

Southern California | Wildfire Mitigation

California launched a statewide effort to clear dangerous vegetation in high-risk fire zones—work critical to preventing catastrophic wildfires, protecting communities, and saving lives.

Opponents sued under CEQA—arguing CAL FIRE’s wildfire experts were wrong about the benefits of brush clearing and that protecting native plants was a better fire prevention strategy than the one selected by professional firefighters. The litigation sent the program back to the beginning stages, delaying critical wildfire prevention work ahead of the devastating 2025 wildfire season.

Price of CEQA misuse:

X icon IMPACT: Statewide wildfire prevention efforts halted across thousands of high-risk acres

Under Prop 45:

Courts must uphold project approvals supported by substantial evidence—ensuring decisions based on credible, recognized science and agency expertise can move forward without being derailed by second-guessing.

Liberty Lane Affordable Veteran Apartments

Redlands | 100% Affordable Housing for Veterans

Liberty Lane was a 100% affordable housing project designed to provide stable homes for military veterans with few alternatives. 

Opponents filed CEQA challenges over alleged “aesthetic and noise” concerns—despite the project complying with applicable standards. After six years of delay and a 70% cost increase, the project ultimately lost its funding entirely—leaving veterans without housing and taxpayers with nothing to show for years of process.

Price of CEQA misuse:

X icon DELAY: 6 YEARS

X icon ADDED COST: $21M

+$262,500 per home passed on through higher rents and fees

Under Prop 45:

All legal challenges must be resolved within 270 days so affordable housing projects don’t lose financing and collapse while awaiting a decision.

Sunrise Powerlink

San Diego | Electrical Transmission Upgrade

The Sunrise Powerlink was designed to deliver reliable renewable energy from solar and wind farms in the Imperial Valley to homes and businesses in San Diego—strengthening grid reliability and supporting California’s clean energy goals.

Under CEQA, the project applicant was forced to analyze more than 100 alternative routes and configurations—including options that were never feasible and some that rerouted transmission lines across state lines and back—resulting in nearly five years of environmental review and more than 11,000 pages of analysis. It then required 70 permits from more than two dozen agencies before construction could begin, adding further delay and cost that is ultimately passed on to electricity customers.

Price of CEQA misuse:

X icon DELAY: 4+ YEARS

X icon COST INCREASE: $80M

Under Prop 45:

Environmental review is limited to one feasible project alternative and a “no project” alternative and all secondary permits must be issued on a predictable timeline—cutting unnecessary delay and lowering costs for ratepayers.

Del Mar Heights Elementary School Modernization Project

Del Mar | Local Elementary School

A local school district proposed modernizing an aging elementary school—upgrading classrooms and improving traffic flow to make drop-off and pick-up safer for families.

Opponents sued under CEQA, arguing in part that modernization would reduce the size of the school field. The litigation stalled construction for years, forcing students into temporary portable classrooms while project costs continued climbing.

Price of CEQA misuse:

X icon DELAY: 4 YEARS

X icon ADDED COST: $8M

Under Prop 45:

All legal challenges must be resolved within 270 days so schools can modernize classrooms and improve safety without years of costly delay.

UC Berkeley People’s Park 

Berkeley | Student Housing

UC Berkeley proposed transforming a parking lot and underused portions of the campus into desperately needed student housing.

After extensive planning, environmental review, a public process and approval, opponents sued under CEQA, arguing the project didn’t sufficiently study “social noise” from future student residents—despite being located on an active university campus.

Price of CEQA misuse:

X icon DELAY: 3 YEARS

X icon ADDED COST: $88M TOTAL

+$80,000 per home passed on through higher rents and fees

Under Prop 45:

Projects must be approved or denied based on clear, pre-existing written rules. Subjective claims not grounded in those standards—such as “social noise”—cannot be used to override adopted standards or block desperately needed housing. 

Estrella Substation and Paso Robles Area Reinforcement Project

Paso Robles | Electrical Transmission Upgrade

This project was designed to strengthen the electrical grid and ensure reliable power for communities across the Central Coast—supporting homes, businesses, and critical services.

Despite its clear public benefit, the project entered environmental review in 2017 and still has not received final approval. Years of delay have been driven in part by disputes over the subjective “visual impacts” and “aesthetic character” of transmission lines—stalling critical grid upgrades while reliability needs continue to grow.

Price of CEQA misuse:

X icon DELAY: 6+ YEARS AND COUNTING

X icon IMPACT: Delayed grid reliability improvements and rising infrastructure costs passed on to ratepayers.

Under Prop 45:

Projects must be approved or denied based on clear, existing written standards. Subjective claims cannot be used to endlessly delay critical infrastructure that communities depend on.

Marin County Single-Family Neighborhood

Marin County | Residential Housing Project

A modest suburban housing project was proposed to add new homes in Marin County, a region with long-standing housing shortages.

Opponents challenged the project under CEQA, arguing the county inadequately considered an alternative proposal with 10 fewer units. After nearly half a century of litigation and delay, the project was never built—eliminating new housing entirely through process alone.

Price of CEQA misuse:

X icon DELAY: 48 YEARS

X icon IMPACT: Project Killed by Delay

Under Prop 45:

Streamlined review and clear rules on project “alternatives” prevent projects from being killed through endless litigation.

Portola Middle School

El Cerrito | K-12 Public School

After Portola Middle School was deemed seismically unsafe, the West Contra Costa Unified School District moved to replace it by converting and expanding a nearby elementary school.

Despite extensive public review and mitigation, opponents sued under CEQA, arguing the district needed to further study the effects of reassigning elementary students to nearby schools. The lawsuit delayed the replacement school nearly four years and cost the district more than $10 million in litigation and construction-delay costs.

Price of CEQA misuse:

X icon DELAY: 4 YEARS

X icon ADDED COST: $10M

X icon IMPACT: Students left in portable classrooms at a seismically unsafe campus.

Under Prop 45:

Legal challenges to essential public school projects must be resolved within 270 days—so students aren’t left waiting years for safer classrooms.

USC University Gateway Project

Los Angeles | Student Housing

In 2007, the University Gateway Project was proposed near USC, adding housing for more than 1,600 students within walking distance of campus and a regional transit station.

A competing student-housing landlord sued under CEQA to stop the project as a part of an aggressive effort to block new competition in the student housing market. The lawsuit stalled construction for roughly two years before ultimately being settled in court.

Price of CEQA misuse:

X icon DELAY: 2 YEARS

X icon ADDED COST: $56M

X icon IMPACT: Housing for 1,600+ students delayed.

Under Prop 45:

Legal challenges to essential housing projects must be resolved within 270 days—preventing bad faith lawsuits from holding approved housing hostage for years.

UCSF Parnassus Heights Hospital Expansion

San Francisco | Hospital Expansion & Housing

UCSF approved a $3 billion expansion of its Parnassus Heights campus to modernize a 70-year-old hospital, meet seismic safety standards, add roughly 200 hospital beds and build 762 units of student and faculty housing. The expansion addressed a critical shortage of hospital capacity: UCSF’s hospitals were consistently full, and between 2017 and 2019, UCSF turned away roughly 40% of requested medically necessary patient transfers because it lacked capacity.

Despite the urgent need, opponents sued under CEQA, raising claims that included the project's potential impact on aesthetics and potential bird collisions. The courts ultimately rejected the challenges—but only after litigation delayed groundbreaking on a major hospital modernization project for years.

Price of CEQA misuse:

X icon DELAY: 2 YEARS

X icon IMPACT: Delayed access to new hospital beds for SF residents, delaying treatment and putting pressure on other hospitals in the region.

Under Prop 45:

All legal challenges must be resolved within 270 days so unsuccessful lawsuits cannot tie up essential hospitals and health care infrastructure for years.

Southeast Gateway Metro Expansion

Los Angeles | Public Transit

In 2017, LA Metro began environmental review for a new 15-mile light rail line connecting historically underserved communities in Southeast Los Angeles County to the regional transit system. The line is expected to serve an area with 1.4 million residents and 600,000 jobs, while reducing traffic, expanding transit access and cutting emissions.

The project took seven years to complete environmental review. During that time, the project's estimated price tag climbed from approximately $3.75 billion to $8.6 billion—a nearly $5 billion increase ultimately borne by taxpayers.

Price of CEQA misuse:

X icon DELAY: 7 YEARS

X icon ADDED COST: $4.9 BILLION IN TAXPAYER DOLLARS

Under Prop 45:

Environmental review for climate-friendly infrastructure projects must be completed within 365 business days, preventing bureaucratic delay from turning into billions of dollars in additional taxpayer costs.

Sites Reservoir

Glenn & Colusa Counties | Water Supply & Drought Resilience

Sites Reservoir has been a state-priority water resilience project for decades. As California endured severe droughts and water shortages, the project spent six years preparing thousands of pages of environmental review.

Nearly a decade after the approval process began, permitting remains unfinished—and the project's estimated cost has increased from approximately $3.9 billion to $6.8 billion.

Price of CEQA misuse:

X icon DELAY: 9 YEARS AND COUNTING

X icon COST: $2.9 BILLION AND COUNTING

Under Prop 45:

Essential water projects must complete environmental review within 365 business days, with enforceable timelines for additional permitting—so critical water infrastructure can be built when Californians need it, not more than a decade later.